The sub work on the heat & air, electric, and plumbing continues in March as it becomes a race against time to get everything in the walls before the sheetrock sub is scheduled to be on site. The pictures show the story. You can also see the pine beams clearly in these shots. This was a "Heather add-on" that I absolutely love. Phillip Fouraker has been invaluable on a lot of this lumber - the pine beams, cedar deck railing and cedar deck roofing, and the pine for the interior ceiling (to be discussed later and completed later this summer). There is a lot of extra wiring upstairs in the office for satellite Internet, etc. I am trying to get everything planned out now so at some point it will be "hot wired for speed" :).
It is clearly a lot of work, a lot of wire, but smarter to do a lot of this now rather than later. Continuing to be excited and amazed.